With the finish line in sight, the crews continued working at their feverish pace. The electrical and mechanical teams made further progress, although they are not quite there yet. There are still lots of wires dangling and unfinished duct work. The drywall crew finished the first floor and moved up to the second floor, while the painters made strides keeping up. The tile work is completed on the first floor and only minor finishing remains in the second floor. The concrete floors have been sealed throughout the building, while the floors at the front were cut and stained (see photo) before being sealed. The character of the building is growing with these touches and next week the big move begins!