The crew is really pulling out all the stops to complete the construction project by our April 15 target date. We made progress on numerous fronts. The two back buildings are practically ready… The ceilings have been insulated, the lighting packages mounted, and the floors sealed (see photo). The north end of the buildings’ exterior has received the first coat of paint. Drywall hanging and taping is continuing throughout the main buildings, as is electrical/lighting work. The low voltage wiring crew has joined the party and is running wires for data (Internet) and phone. Here’s looking forward to another week of significant progress!