The electrical crew continued to work intensively running conduit and wires. There is still considerable work to be done, but we are over the hump. It’s a highly complex electrical project. A significant effort also was dedicated to the exterior of the building. with soft demo work and concrete pouring on the north end. The south-facing structures were cleaned up with a good power wash in preparation for painting. HVAC ducting installation continued inside the buildings. Perhaps the most dramatic development was the hoisting of the mechanical equipment (HVAC and blower) to the roofs with a large crane (see photo). This was delicate work as power lines had to be avoided and some equipment needed to be located on roof platforms a good distance from the crane.